We want to apply HRSP 85-91 to our SAP system.  I went through Mopz transaction and it brought up target stack 14 (06/2015) which includes HRSP 86 & 87.  In the 'Select Stack-Dependent Files' I selected ABAP and the 'Add HR Package' tab.  This brought up all the additional HRSP that are available i.e. HRSP 87 to 92.  I selected 87 to 91.  After proceeding it went through to the download basket and I checked and the additional HRSPs were there.  The stack file was generated.

When I use the stack file in SUM SP14 Patch level 2 and get to the 'Select Support packages you want to include' screen I don't see the additional HR packages in the Calculated Level column. Normally this is where the additional HRSP number would be and I would tick 'Take over calculated level'.  The only value in this column is for Component ST-A/PI.

Can you please assist as to why I am not seeing the additional HRSP in the calculated column?

Many Thanks

Shamshudin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Shamshudin,

Could you please check if all the additional support packages have been downloaded and extracted in EPS/in directory.

If not extract the same in EPS/in directory and repeat the roadmap step in SUM tool.

Regards,

Madhu

Former Member
0 Kudos

Thank you.  When reading your answer it prompted me to double check the selection of the additional HRSP and notices there was one missing and that is why it was not calculating values.

I re did the Mopz transaction selecting all the additional hrsp's and that worked.

Thank you all for your assistance