mir7 / miro

Dear All,

My issue is regarding modification of cost center at MIR / MIRO level.

Actually , while preparing Purchase Order for acct category 'K', user are taking wrong cost center.

While preparing MIR7 / MIRO , cost center is coming from Purchase Order  .

In MIR7 / MIRO,  Cost center is display field in line item.

So can we change cost center while Preparing MIR7 / MIRO.

If yes, then pl suggest me how to change it.

Regards

Swati Shah

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 19, 2015 at 08:36 AM

    Hi

    As far as my knowledge that could not be changed from Miro screen .. but you can post re class entry from GL tab in Miro screen

    Regards

    Mahmoud EL Nady