Former Member

Resource Management Screen Columns - Changing from Week Number to MM/DD

Hello PPM Experts, I'm hoping one of you can help me resolve an issue I have with the Resource Management screen.

By default the Week #'s are displayed on the screen for the Resources and Staffing screens. E.g.:

But I want to display a traditional calendar unit of measure (i.e. MM/DD).

Have you encountered this challenge and resolved it? I'm running PPM 6.1

If so, I'd love to hear how.

Thanks in advance,

Tom Martin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 11, 2015 at 06:52 PM

    OK folks - here's an update:

    I created an OSS message 3 weeks ago and finally got a response.

    Apparently this is how it works and it cannot be configured.

    Changes to the way the weekly periods are displayed is an enhancement.

    I'm closing the message.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 15, 2015 at 09:16 PM

    Hi Tom,

    Check Period value selected as shown in the screenshot

    Best Regards,

    Priyatham


    period.PNG (7.1 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Prayatham, Thanks for your response.

      I have set the Period to Week but need to change the way it is displayed from the standard 40 15 to something closer to 09/14.

      I have searched but don't see a way to configure this. You can hover over each week and it does tell you the calendar week, but I'd like to see that as the default.

      Hope this clarifies!

      Thanks, Tom.