SAP-PS: WBS element oprative indicator

Good day,

unfortunately I cant select the " billing element " in a WBS-element operative indicator ( no matter what level ).
It is an investment project ( object class = Invest )
Field_Selection : Billing ( PRPS - FAKKZ ) is setup to "CAN" . Nevertheless, the checkbox under operational indicator is inactive .


Settlement is not made, but a debit INPUT invoice is posted to FI and is to a WBS element are then assigned as CO-Object.

Are billing elements only adjustable with customer projects (Production)?


Which settings have to be made otherwise for this Fall: Invest Projekct and Biling Elemenet?



Thanks so much & Best Regards

oal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Oct 15, 2015 at 04:00 PM

    Hello Omar,

    Please check the OPUK settings.

    Regards,

    Paulo

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Paulo,

      yes i think it was the Field_Group.

      The Cjheckbox is activ now. We will test ( to post any Incomes) it next week

      Thnaks a lot

      Kr

      Omar

  • Oct 15, 2015 at 11:46 AM

    Hi Omar,

    Have you already posted the cost, if yes, i dont think you can change the indicator

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 17, 2015 at 03:42 AM

    Investment projects are usually capital projects and don't involve billing (posting revenue to a WBS).  There seems to be an inconsistency in your process.  WBS with revenue should be PROFIT.