Hi Team ,

We are new to IBP .


I would like to know is it possible to run IBP on our local S4 HANA server without getting sap hana cloud service.


Regards,

saharoon.s

Accepted Solutions (1)

Accepted Solutions (1)

yeushengteo
Advisor
Advisor
0 Kudos

Hello

There is a on-premise S&OP 3.0 version available.

Please check the product documentation at http://help.sap.com/sop302.

Regards.

YS

Irmi_Kuntze
Advisor
Advisor
0 Kudos

Hi

as far as I know, as of TODAY it is not possible to run IBP  on the same S/4 HANA, if you refer to your ECC system. Maybe you could use the same server with two separated areas, don't know , I am not a technician. But no process integration

- You can run it as stand-alone on a HANA Database, but it must be on HANA, and only in release 3 which has limited functionality. End of the year IBP6 is supposed to be released, so you need to decide if you really want to go with that old release. Many adjustments have been done already between 3 and 4 both in regards to functionality and maturity / stability.

- You can use it  managed in cloud in IBP 4 or IBP 5, or next release IBP 6

- But it is considered for future Releases to have IBP in same S/4 HANA than your ECC system .  However, you will not get detailed timeline

Yours

Irmi

Irmi_Kuntze
Advisor
Advisor
0 Kudos

Hi

as far as I know, as of TODAY it is not possible to run IBP  on the same S/4 HANA, if you refer to your ECC system. Maybe you could use the same server with two separated areas, don't know , I am not a technician. But no process integration

- You can run it as stand-alone on a HANA Database, but it must be on HANA, and only in release 3 which has limited functionality. End of the year IBP6 is supposed to be released, so you need to decide if you really want to go with that old release. Many adjustments have been done already between 3 and 4 both in regards to functionality and maturity / stability.

- You can use it  managed in cloud in IBP 4 or IBP 5, or next release IBP 6

- But it is considered for future Releases to have IBP in same S/4 HANA than your ECC system .  However, you will not get detailed timeline

Yours

Irmi

wnman2005
Explorer
0 Kudos

Hi,

So IBP v5.0 will still required HCI to automated data loads from S/4 HANA?

Will the standard templates still work?

Thanks,

Will

Former Member
0 Kudos

Hello Will,

HCI is the recommended Data Integration tool to upload data to IBP On-Demand.You can also upload load data in CSV format through Data Integration WEB UI available in IBP (it's not automated unlike HCI).