Completion date not updated in IP10

Hi Experts,

Work order is generated from maintenance plan. And work order had been TECOd.

Upon completion of work order, completion date is not populated in IP10.

Please suggest.

Br,

Sandeep

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Oct 16, 2015 at 07:26 AM

    Sandeep,

    Some questions:

    • Does this maintenance plan have multiple maintenance items
    • Has this issue occurred on multiple plans, or just a single plan
    • Are you using any developments in the maintenance plan or work order process? If so, then deactivate these developments and re-test

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 15, 2015 at 09:36 AM

    Hi Sandeep,

    Can you please share IP10 screenshot ?

    Also please refer below note, whether this is related to your issue

    1960778 - IP30/IP10 doesn't take completion requirement into account


    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 15, 2015 at 01:00 PM

    Hello Sandeep,

    If you have used some program to TECO this work order, which is not a Batch program, then too it can happen. Because in such case the program uses a function module to TECO, which often does not update related activities.

    Regards

    KJogeswaraRao

    Add comment