BPM problem with sync interface.

Hi

I got one Abstract/Async and one sync interface in my BPM and I'm getting MESSAGE_NOT_USED error between them, my scenario is RFC to JDBC to RFC(response with different FM) so BPM receives data from RFC sender through Abstract/Async interface but after that interface, I'm getting the that error (MESSAGE_NOT_USED), the weird thing is I got another scenario almost same and its working, I did a new project with exactly the same interfaces, Mappings, interface det., Receiver det., senders and receivers but I'm still getting the same error, even I tried "RFC scenario using BPM--Starter Kit" Blog but same thing, btw everthing is 0 in SXI_CACHE, I'm going to go mad or something, please help..

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

6 Answers

  • avatar image
    Former Member
    Feb 09, 2006 at 04:12 PM

    How are you calling RFC fm from ABAP code?

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 09, 2006 at 04:31 PM

    CALL FUNCTION 'Z_TSSI_INTERFACE_DUMMY'

    IN BACKGROUND TASK

    as separate unit

    DESTINATION 'TSSI_OUTBOUND1'

    EXPORTING

    jobno = jno

    PERSNO = pers

    BEGDA = '20051231'

    ENDDA = '20051231'

    ABSTYPE = 'xx'

    ABSHOURS = '7'

    ABSDAYS = '1'

    FULLORHALF = 'false'

    uname = sy-uname

    date = '20060201'

    time = '110000'

    TABLES

    RETURN = ret

    .

    Commit Work.

    The thing is this abap is working in another scenario, but when I copy the exacly the same scenario, it doesnt work, its weird, btw I noticed that evertime I run any scenario, short dump occurs, its about RFC authorization for XIRWBUSER user but I got the OSS note for that, I applied it but it didnt solve the problem, btw this short dump happens when I run my workign scenario as well.. this is driving me crazy..

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 09, 2006 at 04:39 PM

    short dump problem is resolved, the authorizations are inactive in client 000. but the other one is still there..

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Have you tried doing this...

      In the Integration directory...open the integration process in question, make a change in the "Description", save and re-activate. See this would help.

      I had the error you are having and re-activation of the intergration process in the ID helped my scenario...

      Thanks,

      Renjith.

  • avatar image
    Former Member
    Feb 09, 2006 at 07:25 PM

    I reactivated it 1000 times, nothing is happening, besides I did everything from scratch 3-4 times, it didnt work..

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Is the issue with just this one BPM?

      Pls verify the Status of the Business Process Engine in the RWB....

      go to Runtimne Workbench --> Component Monitoring --> and make sure that the BPE is in the Green status...

      I am just thinking of places to check for errors ..if you have done this already...pls ignore the reply...

      Thanks,

      Renjith

  • avatar image
    Former Member
    Feb 09, 2006 at 10:49 PM

    Thanks for your replies, I found an error in the trace here it is..

    <Trace level="1" type="B" name="CL_XMS_MAIN-WRITE_MESSAGE_LOG_TO_PERSIST">

    <Trace level="3" type="T">Persisting message after plsrv call </Trace>

    <Trace level="3" type="T">Message-Version = 012</Trace>

    <Trace level="3" type="T">Message version 012</Trace>

    <Trace level="3" type="T">Pipeline CENTRAL</Trace>

    </Trace>

    <Trace level="3" type="System_Error">Error exception return from pipeline processing! </Trace>

    <Trace level="1" type="B" name="CL_XMS_MAIN-WRITE_MESSAGE_TO_PERSIST"></Trace><!-- ************************************ -->

    <Trace level="3" type="T">Persisting message Status = 014</Trace>

    <Trace level="3" type="T">Message version 013</Trace>

    <Trace level="3" type="T">Pipeline CENTRAL</Trace>

    Do you have any idea what it is?

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      You have told that u had exactly another scenario. Try deactivating that scenario and execute the current scenario alone.

      Regards,

      Sudharshan

  • avatar image
    Former Member
    Feb 10, 2006 at 03:12 PM

    how can I deactivate it?

    Add comment