Where do I define Capacityconsumption rate? in RESLOCPROD or PRODUCTIONRESOURCE

Where do I define capacity consumption rate. As per SAP2 it is available both in RESLOCPROD & PRODUCTIONRESOURCE master data attributes. CAPASUPPLY is defined at RESLOCATION level. So do I need to define Capacity consumption rate at PRODUCTIONRESOURCE table?

I will be using the consumption rate defined at RESLOCPROD to compute the production load at the resource. So then is it necessary to define it at PRODUCTIONRESOURCE level?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 14, 2015 at 07:57 AM

    Hi Alok,

    For production resource you need to define capacity consumption rate in PRODUCTIONRESOURCE master data. It is required to calculate capacity consumed in production.

    RESLOCPROD is only used of handling resources.

    Thanks,

    Rohit

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.