How to change network costing variant for actual?

Hi All,

I have a network in my project. One Internal activity underneath this network is confirmed. Now I need to change the Costing Variant (actual) for this network. The system gives me error (obviously because activity is confirmed). Is there anyway I can change this costing variant. Since this is a demo project, I am ok to delete the activity or whatever other changes are needed. I need this change because Actual Costs are not getting calculated on the project (because the current costing variant set in this field refers to plan costs).

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Oct 13, 2015 at 01:20 PM

    Hi Ashwini,

    I think cost variant is not the reason for actual cost calculation, not sure.

    Goto opuv and select the network type and change costing variant. and better create new project and try to book confirmation and see whether actual cost is getting calculated or not.

    Thanking you

    Vengaiah

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 13, 2015 at 01:26 PM

    Hi Ashwini,

    You will need a new network with a different costing variant.

    Regards,

    Paulo

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.