Hi guru,

I'm testing the valuation of an equipment. My question is why for one characteristic, the operation is Completed and Rejected (red icon) and equipment is Completed and Accepted (green icon) ? This case is possible ?Where can I found this configuration ? in SPRO ?

Thank you for your help.

Accepted Solutions (1)

Accepted Solutions (1)

former_member42743
Active Contributor
0 Kudos

This is usually based on the valuation of the inspection lot I beleive, not the characteristic.

Just because a characteristic fails dosn't necesarily mean the inspection lot was failed.

What was the UD on the lot?

Craig

aydinhn
Explorer
0 Kudos

Craig,

No other result is encoded.

I've found that after valuation of characteristic, you have to valuate equipment. This is here that you can Accept or Refused the equipment !

But I have another question, is this changeable in custo ?

Regards,

Huseyin

anand_rao3
Active Contributor
0 Kudos

Basically this is the proposal for the evaluation of inspection point. It comes from customization

QCC0 > Quality Planning > Inspection Planning > General > Define Identifier for inspection points > Double click on the identifier that you are using here and go to Valuation tab. You can see here the default code group and codes maintained.

From my point of view these codes are needed here as they automatically propose the valuation of inspection point based on characteristics valuation. What you want to change here?

When you get this pop up while saving, you can very well change it by clicking on Valuation icon as highlight above. No need to change customization for this.

Anand