on 10-09-2015 5:29 PM
Hi,
Quick question, can anyone suggest a PS report which gives you periodic view of planned hours. possibly in fiscal period.
we are not using workforce planning, we just plan hours on internal activities.
But want to see the planned hours by fiscal period.
Thanks,
Krishna
Hi Kirshna,
What is that you are looking for .. I did not get your requirement.
Thanking you
Vengaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vengaiah,
Thanks for responding.
Let me explain..
I have WBS with internal activities and I have planned work on them and scheduled them.
say 500 Hrs spread across 3 months
I am looking for a report which shows
]
Month Planned Hrs Planned Cost
M1 200 10000
M2 200 10000
M3 100 5000
There are many reports for planned cost break up but I couldn't find any with planned hours.
And its ok if I don't have planned cost in the same report. I just need the planned Hours in a monthly breakup for a WBS
Thanks,
Krishna
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.