SAP HANA System Migration (Only Storage Migration)

Hi SAP Experts

I have an SAP HANA (BW on HANA) system and I would like to migrate only the underlying Storage with out changing anything else. What is the best migration approach to do such kind of storage migration. I don't want to create a new SAP HANA system do an export from using Source and Target approach. What is the best way to do this kind of storage migration for Applications on SAP HANA with out any downtime if possible.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 12, 2015 at 07:19 PM

    Hi Krishna,


    Can you please elaborate on the your setup

    Which version of HANA are you using?

    What kind of Backup setup you have in place?

    If there is a HA/DR setup based on SYSTEM Replication or Storage Replication?

    I have not come across any document that describes the standard solution to be used for HANA Storage migration with least downtime as I believe it entirely depends on the solutions that you in place.

    Most importantly Storage migration is possible with the TDI setup so you are bound to have solutions available from the storage provider and not necessarily from SAP that can be standard

    Please provide more information on your setup that will be useful to make any suggestions

    Sunil

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Krishna,

      If there is no HA setup in the same Datacenter we may have few options to accomplish the storage migration with least downtime

      Involve the Storage vendor on this they would start the migration of the data on current storage to the new Storage disks

      Most vendors offer solutions that can do this online


      Make sure the data is migrated to the same disk layout as you have currently setup on your HANA system

      However there will be a downtime involved to do the switchover of storage on your HANA appliance

      The outage duration for the migration will depend on the time the Storage Administrator needs to un mount the existing disks and mount the new disks

      Again we do not have any SAP standard document that I have come across for this

      Let me know if you have any other questions

      Sunil

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.