Hello everybody!

With note 1953429 it is possible to install HANA and AS ABAP on 1 server. We plan to migrate our SAP BW 7.40 to HANA.

My question: Where do we put AS Java that is in place?

Best regards,

Gerald

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 09, 2015 at 05:37 PM

    Hi Gerald,

    You have 2 options to place the JAVA instance on HANA system

    1. Up to version SPS08: Create a new schema for JAVA on the same HANA instance along with ABAP. It has a few challenges with System refresh from Prod to non prod that will have the JAVA system automatically refreshed

    Please refer below documentation for more inputs

    http://scn.sap.com/thread/3683255

    2. From SPS09 you could set up a Multitenant Database container(MDC) setup and create a dedicated JAVA instance along with another instance for ABAP

    You can refresh the ABAP instance alone in this setup without any impact to the JAVA instance

    Hope this helps

    Sunil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.