Still open in Release Step 'CK40N' . . .

Hi Experts-

I am facing one issue in CK40N costing run...

I am doing costing run At selaction stage i have selceted 2057 and at structure.Exploded to 2468 and in Marking step 2468 but in release step 2467 and still open 1 Material .

My concern is there any log analyses showing Material code and why system showing those materials

Please give suggestions....

Thanks,

Emad Gamal

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Oct 08, 2015 at 03:12 PM

    Hi,

    the statistic only shows the numbers that have been processed in that step. Most probably the 'missing' material has been released by another costing run, CK24 or dynamic price release. Therefore it is not included in he statistic.
    Please see SAP note 1680489 which explains how to display a better statistic.
    Note 1321242 is also helpful if you have 'Still Open' materials.

    If you have 'Still Open' materials in the costing step then usually this is caused by a cancelled task during parallel processing - so, please check the message log in this case.

    Regards,
    Johannes

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Emad,

      the statistic of CK40N is not incorrect. The 'Still Open' material has not been processed in the release step (it was released by dynamic price release or CK24 posting) - the CK40N statistic only shows what has been processed in the costing run steps.

      You can update the statistic in CK40N by OK-Code CKSU

      Please note that CKSU should only be used if you do not want to further analyze why 'Still Open' materials are shown.

      Best regards,

      Johannes

  • Posted on Oct 07, 2015 at 10:34 AM

    Hi,

    At each stage you will get the message log, you can get the list by clicking the error log.

    One more thing:

    If you are not comfortable with cross checking the missing material with the said procedure, please use the following procedure:


    Get the list of materials before cost estimate and after cost estimate from the following report, then compare you will get the missed out material.



    Then do cost estimate for that single material using the T code: CK11N, you will get the detailed message log.....

    Regards,

    Pavan Kumar Arvapally


    CKApp01.jpg (66.6 kB)
    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Emad

      You have all 2468 material list at 'analysis' step, take that list and in MM60 fill those materials.

      Check last change column it should be filled with costing date, only for missed material the date will be older one. This is not a universal check because 'last change' column is meant for any changes in the material master, but this time it can work because the latest change is due to calculation of standard cost.

      Regards

      Rajneesh

  • author's profile photo Former Member
    Former Member
    Posted on Oct 07, 2015 at 12:04 PM

    HI.

    You can use a report S_ALR_87099930 - Результаты прогона калькуляции

    You can find a material with the status VO


    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.