Lifecycle planning not taken into account for the stat forecast job

Former Member
0 Kudos

when i run the constant stat forecast manually, i see the tick for lifecycle planning (in the setting tabs) and the stat forecast is until jan 2016

but the output of the stat forecast job is not the same as when run manually.

By background Job when run the forecast even Lifecycle planning active in master profile ....after Phase out profile also forecast generating could you please tell use what is the reason

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For the successful PIPO the below steps required.

1)valid CVCs for both products

2)Like profile(with both old and new)

3)phasein/out timeseries

4)in master forecast profile tick life cycle planning active.

5)run univariate for new product.

Thanks,

Naga.

Answers (1)

Answers (1)

satish_waghmare3
Active Contributor
0 Kudos

Hi Srini

Please elaborate your question in detail. At the moment, it is little confusing to understand the scenario.

Thank you

Satish Waghmare

Former Member
0 Kudos

Hi Say example :

for the 2 following articles, i created a phase in profile in week 36 and ran the statistical forecast manually

X and Y

so at the end of week 36, stat forecast generated.

In week 37 on  statistical forecast job ran again, ( Back ground )

the outcome of it was obviously 0 on the entire horizon

the 2 articles are in the selection : say example Z this selection is there in back ground job step and to generate forecast which is using master profile in that life cycle planning is active

so this method should have been applied during the stat forecast run in week 37. as 2 products maintained in Phase in profile i am expecting forecast and it is working fine in interactive mode

why did it not happen this through batch job way ?

*

satish_waghmare3
Active Contributor
0 Kudos

Hi Srini,

I could understand that you are able to use life cycle planning only if forecasting is carried out interactively in Planning book, but it is NOT happening when it is run using DP Background job.  Although your master profile has Life Cycle Planning checkbox selected.   Sorry, Other than this I did not understand much from details given by you.

I suggest you to check following steps are done correctly SAP Menu- Demand Planning → Environment → Lifecycle Planning->

1. Basic settings for the planning area

2. Creation of Profiles – Like Profile, Phase-In and Phase-Out Profiles, whichever is required.

3. Assignment of the profiles to individual characteristic value combinations.

Also read more about Life Cycle Planning in APO and usage each of these profile at below link -  Lifecycle Planning - SAP Library

If possible share screenshot of your basic settings, Ph-In profile, Assignment.

Thank you

Satish Waghmare

Former Member
0 Kudos

Hi,

All required settings maintained correctly but still it is not generating forecast by background job but when we do manually interactively it is working fine .

Regards,

Srini