Issue in Planned Delivery Time and GR procesing time in MRP

Hello All,

I have an issue in delivery date calculation for Schedule line. Here I am creating Schedule line w.r.t requirements from Sales Schedule agreement. with backward scheduling (material in both sales and MM schedule agreement is same). I have given GR processing time as 42 days both in material master as well as the Schedule agreement. And Planned delivery time as 10 days in info record, Schedule agreement. my requirement date as per sales Schedule agreement is on 31.12.2015 and when i run MRP Schedule line is generated with delivery date 31.12.2015. GR Processing time and Planned delivery time is not considered in the MRP run.

I have already check many threads in the forum and i have checked on the following points.

  • OMDT- under Plant Scheduling: info rec/Agreement check box in flaged and Automatic Schedule lines is set to 3 (Schedule lines)
  • In source list source list usage in material planning is given as 2- Record relevant to MRP. Sched. lines generated automatically
  • In material master, MRP Type- PD, Lot size- EX , Procurement type- F, Availability check- 02   
  • in MD02 screen Processing key- NETCH, Create purchase req-1, Delivery schedules- 3, Planning mode-1

Kindly help me out to overcome this issue.

Regards,

Manoj

Source list.JPG (47.3 kB)
MD02.JPG (68.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Oct 06, 2015 at 08:38 AM

    Dear,

    Please follow below link.

    Best regards

    Shailesh Mishra

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 07, 2015 at 09:59 AM

    Hello Manoj,

    The date that is displayed in MD04 is the delivery date of the goods in the schedule line, and not the shipping date.

    The MRP implicitely uses your GR processing time and the planned delivery time just to check if the requirement date can be met (which is true for your case). Otherwise, the delivery date in MD04 will be set later than the requirement date.

    I hope this helps.

    Regards;

    Taher.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 07, 2015 at 10:37 AM

    Please double click on the schedule line and in the element detials check the delivery date. This is date that material will be availble in your plant. The date is calculated based on the planned delivery time.

    The date shown in the MD04 is the Material avaible date for the requirement.This includes GR processing time.

    Please check and let me know your feedback