Skip to Content
avatar image
Former Member

Underdelivery and Overdelivery Tolerance For MTS products

Hello,

SAP provides the underdelivery and overdelivery tolerances for MTO products only. We have a requirement at our client where One bulk order is used by multiple finished order. Due to SNP planning, the quantity of bulk order may not always exactly match the quantity of finished order in that bucket. In case of deficit of quantity of bulk order, the finished product will be pegged to bulk order of next bucket. So when scheduling is performed on such orders, the finished product order will be delayer.

So we are looking for a way so that we can influence the pegging between bulk order and finished product order using under and over delivery tolerances.  we have an alternative where we can create fixed pegging using custom logic. But it has its own challenges in case of manual scheduling.

Is there a way we can influence this pegging dynamically using custom logic?

Looking for suggestions to resolve this issue.

Regards

Chintesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 02, 2015 at 07:31 AM

    Hi Chintesh,

    the topic is very difficult in MTS because you do not have a specific tolerance per pegging arc.

    Pleasse have a look at the following SAP notes:

    1250779 Underdelivery tolerance at component level

    875667 Underdelivery tolerance in the SAP_PP_003 heuristic

    663313 Implementingunderdelivery tolerances from SO as of APO 4.0

    Frank

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks a lot Frank for quick response. Apart from creating our own fixed pegging based on tolerances, do you have any other ideas as client is not comfortable with fixed pegging as its MTS scenario.

      Regards

      Chintesh