can I set up my task in sm37 (or other) to not start in specyfic time? I have tasks witch run every hour but in every sunday i have backup and my task end with error. I want set up, that task do not start in every sunday after 11:00 p.m. Can someone help?

Best regardas

Hubert

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Hubert,

You can leverage "Restrictions" option on the scheduling window for custom schedule. Check if any existing options like excluding on sundays will work for you. If not, then create factory calendar to create schedule based on your custom needs and configure that for scheduling your job.

Here is link on how to configure factory calendar.

Thanks,

Chiranjeevi.

Former Member
0 Kudos

Hi Chiranjeevi,

thank you for answer, but in factory calendar i can canfigure specyfic days. For example "each first monday in a mounth is a holiday". But i need plan more specyfic. In every sunday on 11:00 p.m i have backup witch kill all runing tasks and i want configure my planned task to not run after 10:00 p.m in each sunday. I don't see that posibility to configure in factor calendar.

Thanks,

Hubert

Former Member
0 Kudos

Hi Hubert,

Schedule two different jobs, one to run during week days. Another to begin at 10:00 PM on a Sunday only.

Thanks,

Chiranjeevi.

Former Member
0 Kudos

Hi,

i can plan in two different jobs, but i have 15 jobs witch have 5 steps and each run in every hour and i wonder if i can plan one task and set up specific conditions to not run this job after, in this case sunday 11 p.m. I'm very curious how can we do this.