Hi,
We are following the Below process for MRP Materials Procurement
Reservation-PR-PO-GR-IR, and budget check is there only at Reservation and GI Creations level;
when i am doing the changes to price in Reservation FM Document through FMX2 , Sytem is giving the below error.
we want to update new MAP price afer PO Releasing in Reservation FM Document.
After Selecting the Account Assignment Changeable indicator,
again below error is coming.
Thanks & Regards
SAM...
Hi, you need maintain tolerance in view V_FMR_TOL, then assign it to your doc type in tcode FMU1
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amar,
Below is the process we would like to do.
1. Reservation Creation - EF Document created with price $10 Per unit
2. MRP Run-PR
3. PO - If Price of the Material changes to $20 per unit.
We are calculating the MAP before doing the GR in PO Release transaction and arriving the latest MAP, say $15 per unit it is calculated.
Then we would like to change this in EF Document which is created in Reservation.
means from $10 per unit to $15 per unit.
when i am doing this change, for some EF Documents i am able do the change, but some i am unable to do change becasue of the error.
And Very sorry for the incomplete details in my prevous reply.
Thanks in Advance,
SAM...