Changing Control inspection lot settings in QM

Dear Sap Geniuses

I have an issue for one plant we are STO goods into and we are also procuring the same materials off vendors. So 08 gets generated for the STO and 01 lots for the direct PO's easy. Problem is the one plant they are coming into is set up into 4 different Storage locations and they will always go into Pole 38 location before coming up into the actual production sloc so the 08's are popping up all over the place. Is there any way to change the control inspection lot to be plant material and batch based instead of material, batch and Sloc based. Any help would be great thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Sep 03, 2015 at 12:33 PM

    Hi Sinead,

    You may check the below EXIT in case if they helps -

    QPL10001  QM: Inspection lot creation - editing work area on creation

    Thanks,

    Arijit


    Add comment
    10|10000 characters needed characters exceeded

  • Sep 03, 2015 at 04:29 PM

    I imagine it's more becasue of the material movement you are using.

    I'm guessing  they are using a 311 or 411 to make the moves between storage locations?  What some places do is copy the 311 or 411 movement to a 9xx movement (911).  The 9xx movement is set in config as not QM relevant and as such, no inspection lots will be created.

    Train the personnel to use the 9xx transaction most of the time.  Only use the QM relevant movement type when you want the lots created.  It looks like the issue is when the material in the four storage locations, is moved to the Pole 38 storage location or the actual production storage location,  Make sure they only use the non-QM relevant movement type when moving into these storage locations.

    Craig

    Add comment
    10|10000 characters needed characters exceeded

    • Yes. and that is exactly what I explained how to avoid.  I didn't say change the movement you use for the STO's.

      I said copy the materail movemnt and make the new one non-QM relevant.  Then use the new one for your internal movements, (NOT for the STO).

      Craig