I am doing 03 inspection in production order and system is picking routing as a inspection plan as per standard SAP.

Just to reduce the master data maintenance, I want to use different routing for different material but same inspection plan for 03 inspection.

I tried the user exit EXIT_SAPLQPL1_001 but this is not working for 03 inspection.

Can anyone Pls let me know how to achive this in SAP.

Regards

AK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 02, 2017 at 07:00 PM

    You can't. 03's use the routings.