Hi,

I am doing 03 inspection in production order and system is picking routing as a inspection plan as per standard SAP.

Just to reduce the master data maintenance, I want to use different routing for different material but same inspection plan for 03 inspection.

I tried the user exit EXIT_SAPLQPL1_001 but this is not working for 03 inspection.

Can anyone Pls let me know how to achive this in SAP.

Regards

AK

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Craig S Feb 02, 2017 at 07:00 PM
0

You can't. 03's use the routings.

Craig

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Have you looked at using 04's with early lot creation? Then you could utilize the same inspection plan.