Rejection code for UD of inspection lot.

Hi Experts,

Could you please suggest on the issue.

While doing UD for a specific inspection lot if i am providing the Accepted code then the stock is moving from quality inspection to unrestricted use, but when i am providing the rejection code system is throwing error " 100 qty incorrect posting to block stock." Deficit of BA unrestricted -use 100 qty".

Is it not possible without moving the stock to blocked stock only the rejection code will update in the inspection lot.

Please help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 28, 2015 at 02:41 PM

    Hi Arijit,

    Thanks for the reply.

    Yes i want to post the UD code = R, without physically posting quality stock to blocked stock. Please help.


    Regards

    Akash

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Akash,

      Please can you share the below screenshots for further understanding -

      a) QA11 Screenshot (Stock tab)

      b) MMBE quality inspection, Unrestricted use, Blocked stock status.

      c) QA32 - Inspection lot status.

      Please note that inspection lot with "REL" status but having NO quality stocks linked to it, meaning the linked Quality stock has already been moved out of inspection lot using QA11 - stock posting tab!! As UD code "R" is linked to stock posting proposal to blocked stock, now it becomes impossible to post the same.  There seems to be no further stock available to be posted inside the inspection lot, as that has already been posted manually. Hence the error message seems to be  correct.

      Please can you investigate if someone has used MvT 321 to post the material out of the inspection lot and posted to unrestricted use stock.

      Thanks,

      Arijit

  • Aug 28, 2015 at 02:01 PM

    May be this could be an issue associated with the inventory posting proposals maintained in customization. Could you please confirm what movement types are maintained in below path against VMENGE04? Under Q stock it should reflect 350. I suspect in your case it is trying to pick the stock from unrestricted.

    QCC0 > Quality Inspection > Inspection Lot Completion > Define Inventory Posting

    What do you mean by your last sentence? You want to give UD without stock posting? That is feasible but what would you do with the stock that would still lie in QI? In a day or two or at some point in time you have to make the stock posting for that stock. I think you should first check why the system is not allowing to post the stock to blocked stock!

    Anand

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Anand ,

      Thanks for the reply.

      As i checked my setting for VMENGE04 the movement type has assigned as 350.

      my query is that " Is it possible to do a UD Reject without any stock movement like the same as UD Acceptance?.

      With Regards

      Akash

  • Aug 28, 2015 at 02:19 PM

    Hi Akash,

    Please can you explain what do you mean by "Is it not possible without moving the stock to blocked stock only the rejection code will update in the inspection lot."? I do not understand what you are trying to do. Do you mean you want to post the UD code = R, without physically posting quality stock to blocked stock?

    Please be informed that once the UD = A has already been applied, then the stock locked under quality inspection will be moved to unrestricted stock. The same will be reflected in MMBE screen too. So there will be no further stock logged under the same inspection lot so re-do UD = R.

    In case if UD = R is getting applied at inspection lot level, but the stock is still lying under quality stock, this means that posting proposal linked to rejection UD code is not maintained.

    Please check and suggest if still there is any issue.

    Thanks,

    Arijit

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 01, 2015 at 07:17 PM

    Recheck the configuration setting suggested and see whether 350 is maintained under Q-stock or 344 is maintained.

    What seems to me, you're trying R to post the quantity to block from QI and you need 350 for that. But looking into error, system is looking for posting it to block but from UR and hence, 344 comes into play.

    If possible, share the Inventory posting screen shot along with complete status of inspection  lots and steps followed in the process. It is important to know at what stage this error is coming and what exactly is already done until that point.


    NJ

    Add comment