Start date of Project definition / Network shall be in Past

hi Friends,

As in subject line, We are trying to set-up a Project with Start date in Past (Ex. to be in Jun-2015). However, I am Unable to change Project Start date: (to a Past date).


Network Scheduling type: Backwards; Scheduling scenario: Strict Bottom-up @ Project Definition level.


For WBS-1 which has Network .01 with 3-activities ending on let's say 10/25/2015. Finish date given in Network header so that the relevant Activity dates are calculated.


Act.1 27

Act.2 46

Act.3 63


When Scheduled and withing CJ20N screen, the Network header displays the scheduled Start in Past (based on Activity duration) & Finish date as entered 10/25/2015 . But, when I click on Save & Re-open the project, System automatically sets the Network Start date to Current system date on Network Header & determines a Finish date based on Activity 0010- 0030 duration, IF Scheduling carried out results in a Past Start-date. IF the duration of Activities is reduced such that Activity 0010 has Start date beyond Today's date: 26-Aug-15 for example, Network header dates are updated & carried way up-to the Project definition the way it's supposed to be.


For WBS-2 which has Network .02 with activities ending on let's say 12/20/2015


Act.1 33

Act.2 41

Act.3 25

System calculates the dates and Network header updated with scheduled dates (as Act.1 has Scheduled Start date beyond Today's date & Finish is after Today's date).

Q: How can I achieve the system to store the Network header dates even when Schedule start goes to Past date from Current system date, so that the Project Start date is also updated to a Past date?.

-Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Best Answer
    Posted on Aug 26, 2015 at 12:54 PM

    Hi,,

    Please check your below settings,

    1. Specify Parameters for Network Scheduling (TC. OPU6)

    A) Select your order type

    B) Give Start in the Past value as "999" and save.

    2. Define Parameters for WBS Scheduling

    A) select your WBS scheduling profile

    B) Give Start in the Past value as "999" and save

    ~With regards,

    Dnyaneshwar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.