Cost Analysis in COR3 (process order)

Former Member
0 Kudos

Hi Experts,

When I display a process order in COR3, I can drill to the cost analysis report by clicking on Goto>Costs>Analysis.

When I view the report, for quantities, the report is showing the planned quantity in the Total Actual Quantity column, and the actual quantity is displayed in the Total Target Quantity; just the opposite of what it should be.

I'm not sure how to fix this.  Is this a type of costing sheet that is defined in Configuration?

Thanks and regards,

Judy Ortscheid

Accepted Solutions (1)

Accepted Solutions (1)

ameya_beri
Active Contributor
0 Kudos

Hello,

Please check configuration transactions OPN2(valuation variant) and OPL1 (costing variant) for the settings.

Also discuss the problem with a CO consultant

Best Regards,

Ameya B.

Former Member
0 Kudos

Thanks Ameya.

I've been going through configuration and this seems to be a bit complicated.

I also looked in table COSS and it appears that for Delivery Expense Overheads, the plan, actual and target all have the same value.  This must be a basic mapping error somewhere.

I appreciate your help.

Thanks again,

Judy