IM to SAP-PPM - budget

SAP PPM 6.0

We have identical Portfolio structure (SAP-PPM) and IM structure.

IM is where the budget will be allocated to the nodes and we are looking at moving over this figure (budget) to the corresponding Portfolio Structure node (bucket).

What will it involve?

Thanks.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 25, 2015 at 10:41 AM

    Hi Deepak,

    You need to Define financial Category for "Budget" and then define Financial views for budget..

    this will allow you to map your budget values at the bucket or Item level..

    For the budget amounts maintained in IM to reflect in PPM. You need to write a custom program for uploading the data.. I don't think it is available in standard..

    Regards

    Sammar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.