Pl let me know what this heuristic SAP005-Schedule Operations-/SAPAPO/HEUR_DISPATCH

Hi

Please suggest what this Heuristics(SAP005-Schedule Operations,/SAPAPO/HEUR_DISPATCH) does for deallocated planned orders:

We are getting Deallocated Planned orders when we run the Rescheduling job,Requirement is not to get deallocated planned orders

when i see in google there is one Huristics "SAP005-Schedule Operations,/SAPAPO/HEUR_DISPATCH" for the below link

http://help.sap.com/saphelp_scm700_ehp03/helpdata/en/e7/4dc95360267614e10000000a174cb4/content.htm


Please suguest to use the delocated planned orders

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 25, 2015 at 09:29 AM

    Hello,

    During rescheduling of operations, the planning horizon period is always taken from the time profile.

    Please check all your operations comes under time profile

    Also check strategy settings of the current strategy profile and the Log of planning run is there free available capacity to schedule these operations.

    Best Regards,

    R.Brahmankar