Skip to Content
0
Former Member
Aug 21, 2015 at 10:05 AM

actual cost value in calculation of remaining order plan

63 Views

hello,

In calculation of remaining order plan value, plan values of the material which are maintained as project stock (indicator 2) are not considered in remaining order plan but when these materials are issued to production order, that actual cost are being considered in calculation of remaining order plan. This results in lower value of remaining order plan calculation which is wrong.

Can you please suggest the way so that actual cost of such materials should also not be considered in calculation of remaining order plan value.

Regards

Kalpesh Agrawal