After running KSPI the Schedule Activity is copied to Plan Activity in KP26, but Capacity Field isn't updated , how can i upload this field automatically ?Thanks for your help.
Hello Cris,
KSPI is used to calculated the plan price of cost center/activity type.
Do you mean KSPP?
There is also a note :
41621 KSPP: Preconditions for transferring activities -> good
Best regards,
Jason