Solman SP Stack Upgrade from SP3 to SP12

Hello,

Can anyone please let me know what basic details i need to check for SPS upgrade in Solution Manager 7.1 from SP3 to SP12?

do i need to download the CD from the Service Market place or i need to generate the stack.XML file from Mopz??

Also I want to know can i directly upgrade from SP3 to SP12 or do i need to first upgrade to SP8 and then to SP12??

Thanks & Regards,

Vishal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Aug 20, 2015 at 04:07 AM

    Hello Vishal,

    By generating the XML file from MOPZ you can go ahead with upgrade.. and you can go directly from SP3 to Sp12.

    Hope this information helps.

    Regards,

    Karthik

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 20, 2015 at 04:15 AM

    Hi Vishal,

    You need to generate the stack file from MOPz.

    Also please check the below note, which will help you for the recommended corrections.

    2106807 - Solution Manager 7.1 SP Stack 13: recommended corrections

    Further check the below note

    1577909 - Enhancements for SAP Solution Manager 7.1 SR1

    Thanks

    Rishav

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Rishav,

      Thanks a lot for your response. I am currently trying to solve Mopz issue.

      Regards,

      Vishal

  • Aug 20, 2015 at 09:43 AM

    Hi Vishal,

    You can directly upgrade to SP12 or SP13 as per your requirement by generating a stack file from Mopz in your current solman Sp03 system.

    further use SUM(latest version) to upgrade both stacks together to sp12 orĀ  sp13.

    In addition please find below some good documents on this topic

    https://websmp202.sap-ag.de/~sapidb//011000358700000911492011

    https://websmp110.sap-ag.de/~sapidb/011000358700001315982011

    Thanks

    Prakhar

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 21, 2015 at 04:01 AM

    Hi Vishal,

    Connect SOLMAN ABAP and JAVA to the SLD.

    Sync this SLD with LMDB and SMSY.

    Complete the modelling of solman system in LMDB/SMSY

    Assign logical component to solution manager system and and put it into a solution.

    Once done, then run LVSM and make the adjustment.

    Then use MOPZ to select the solution and generate the stack for solman.

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 23, 2015 at 02:20 PM

    You can download the SP12 CD from SMP and use it. it contains the stack file as well which will be used by SUM to update your solman SPS. Regards Munish