SAP APO GATP partial Confirmation not rounding

Feb 02, 2017 at 06:29 AM

67

avatar image

Hi,

I have sales order in which order qty of 39 is rounding to req. rounding qty 40 whereas during GATP availability check the round is not happening. say Unit of Measure is maintained as 2 PC =1 Pallet.

Partial confirmation is happening for 27 qty, whereas confirmed qty should be 26 as per Business requirement.

partial.jpg (44.4 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Mohit Bhagat Feb 17, 2017 at 07:20 AM
0

Hi,

GATP always gives confirmation based on Base unit of measure. There is no standard way to check and confirm based on Sales Uom. So you might have to use the below mentioned user exits to solve the issue.

EXIT_SAPLATPC_002

/SAPAPO/ATP_REQ_ITEM_CONF

Regards,

MB