Scrap management in PP module

Former Member
0 Kudos

hi,

i need some help with scrap management issue.

where i can find a documentation of standard sap for scrap material management.(if you can send me link it will be a huge help).

when I add new operation for scrap in C202 tcode and perform process order with weighing the componets not disposal.

in process order I can see after the first perform mvt 101 with mvt 261 for components and its OK but in the next step when i perform the second step of scrap i get mvt 531 for scrap material in minus and the stock increased in MMBE only for scrap material.

anyone can tell me if this is procedure of perform scrap from process order??i attach screenshot.

regards,

Amit Berku

Accepted Solutions (1)

Accepted Solutions (1)

Amit_SAP
Active Contributor
0 Kudos
Former Member
0 Kudos

Hi Amit,

Thank you for your quick response but this is not what I'm looking for, I search for a way to use the current BOM without changing quantities of items in it and maybe by a BAPI or any kind of function the scrap will be added to stock with 531 movement and other items that connected to this scrap material will be decreased in stock.

By the way, not connecting at all to the currect disccusion, I know that Amit is a Hebrew name that means a friend, I never saw this name in other countries, what is the meaning of this name in your country ?

Regards,

Amit Berku

Answers (1)

Answers (1)

former_member196530
Active Contributor
0 Kudos

http://wiki.scn.sap.com/wiki/display/ERPLO/Scrap+Calculation

Hi ,

Frist of all , if you have mapped your scrap as bi-product having low value compare to main product either in BOM or in Process Order Component level. If you do not want to disturb your BOM  , you can add n  no of times for any  scrap material code in Process Order Components view  and assign that material in a spefic scrap operation , then it will reflect in the activity confirmation if its subject back flash as per MMR setup or mark in BF in PO component view Or it will show up in MIGO screen .

Please refer the above link  documents for scrap management.

Regards

JH