CM25 process orders rescheduling

Hi,

Please look into the below case and suggest,

1. Transaction CM25, all dispatched process orders are first deallocated and then again allocated.

2. Then out of the dispatched orders I deallocate some orders for example 3 orders and again dispatch those in some future date in the middle of the schedule.

3. I found that one of the order starts at exact 00:00 midnight and hence overlaps an existing order which has already started the previous day and not yet finished.

4. In some cases if the above steps are performed there is no issue i.e. the orders are scheduled after the finish of the previous order.

5. Forward scheduling, Finite scheduling is used in this case.

Can you please suggest why this kind of behavior.

My requirement is the orders should not appear in parallel on the same time i.e. should not overlap. And get scheduled as per the input date given during re allocation.

Please inform if more inputs are required.

Thank you for you support.

Regards,

Vishal

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Aug 17, 2015 at 11:53 AM

    Vishal,

    Check Operation date check function in the strategy profile and also check close gaps setting.

    BR
    KK

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.