Spliting of purchase requestion document types when Auto PR is generated via Plant maintaince Order

Feb 02, 2017 at 04:17 AM

157

avatar image

Hi

We have below requirement to splitthe document types in ZNB and ZSRV if user enters Control key PM01 and PM03together

Where PM01 has item category as “n”

as well as it will have PM03 for services

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Peter Atkin Feb 02, 2017 at 11:55 AM
1

Have a look at the following user-exits via transaction SMOD:

  • COZF0001 Change purchase req. for externally processed operation
  • COZF0002 Change purchase req. for externally procured component

PeteA

Share
10 |10000 characters needed characters left characters exceeded
vishhal bubane Apr 14, 2017 at 12:45 PM
0

Hi

for Plant maintenance this is resolved with Configuration ... without using exit .

Path

Plant Maintenance and Customer Service - Maintenance and Service Processing - Maintenance and Service Orders - Functions and Settings for Order Types - Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval

regards

Vishal Bubane

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Vishhal,

With respect to config you have mentioned, it is possible only for one document type, so it is not possible.

Also your request is to have different document type with respect to control key, thats not possible in standard.

As Pete mentioned, this needs to be handled through exit only.

Regards

Terence

0
Manikandaraja P Apr 16, 2017 at 11:57 AM
0

Hello Vishhal,

You can use either Business Add In "IWO1_PREQ_BADI" or the user exits as Peter has mentioned. Please do check these with a technical consultant.