on 08-14-2015 3:19 AM
Dear SAP Gurus,
1.If ‘A’ is a phantom material having set of parts. Set of parts are B, C and D. What is the configuration required to sell or procure these three parts in a set?
2.What is the difference between, if I set the phantom assy in MRP-2 (special procurement key-50) view rather than in BOM item? Please give example on both cases.
Thank you,
Regards,
Sudip
Hello,
A phantom assembly is a virtual assembly.
For 1: For a phantom assembly the requirements are directly passed on the components, so to procure B,C,D in a set, you should check the explosion type indicator in the BOM.
For 2: If you set the indicator at MRP 2 level it will be applicable to all the BOM's the material is a part of, if you set it at BOM item level it is only specific to the BOM.
Please check SAP help for reference:
BOM Explosion with Phantom Assemblies - Material Requirements Planning (PP-MRP) - SAP Library
Best Regards,
Ameya B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.