Hi Friends

I want to post actual labour hours in C015. I dont see any field in C015 to enter actual labour hours manually.

When I use C015 for production order final confirmation, it takes planned hours from the routing master data and post as a actual hours. But I want to enter the actual labour hours in C015 before posting. Is there a way or any other transaction.

CO11N is the only way or is there any other options ?

Thanks/Regards

Vijayasankar. R

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member185450
Active Contributor
0 Kudos

Hi Vijay,

you are doing the operational level confirmation hence suggesting to use CO11N transaction(Operational confirmation against production order) instead of CO15 header level confirmation)

similarly OPK0 is the transaction code you can choose the screen selection

Regards,

Venkatesh..

Former Member
0 Kudos

Is there a way or setting change will help to post actual hours in CO15?

I dont want to use CO11N by operation because other business reasons

Regards

Vijayasankar. R

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

There is no setting to do that. You can explore BAdI WORKORDER_CONFIRM to create a custom code to do that.

former_member299289
Participant
0 Kudos

Dear Vijayasankar,

You may use CO11N as advised and probably you can explore configuration OKP0 to change the screen layout accordingly.

Thanks

Karthik

Former Member
0 Kudos

Hi Karthik

Thanks for your option. Is this OKP0 transaction code is correct?

It says the transaction code does not exist.

Regards

Vijayasankar

former_member299289
Participant
0 Kudos

Dear Vijaya Sankar,

Sorry for the Typo. Its OPK0

Former Member
0 Kudos

Is there a way or setting change will help to post actual hours in CO15?

I dont want to use CO11N by operation because other business reasons

Regards

Vijayasankar. R

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please observe that, on transaction CO15, you are posting a confirmation at order level, therefore, you don't have the details of each operation. According to the SAP help, when posting confirmations at order level, the planned values are posted for the operation activities.

Try to use CO11N or CO12, where you can define the actual values for the operation activities.

BR
Caetano

Former Member
0 Kudos

Is there a way or setting change will help to post actual hours in CO15?

I dont want to use CO11N by operation because other business reasons