Hi All,
Need your help on below Issue.
We are facing issue in the planned order being sent from APO to R/3. Planned orders are of type LA (Stock Order) and E as procurement type, whereas it should come as NB (order type) and 03 (subcontracting) for special procurement type for LB profile. Hence facing issue in converting planned order to purchase requisition, where wrong pur. req type is coming and item category L (sub contracting) is missing due to above issue. We can change it manually but it should come automatically.
If we make product PD, MRP relevant and run MRP run, the planned orders are created of correct type NB
Is there any setting in APO where we can map order category with APO and R/3.
MRP profile is correctly maintained for subcontracting in OMDT.
please find attached for issue detail.
Thanks
Navneet
Hello
Did you maintain the special procurement type 'subcontracting' on the material master tab MRP2?
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.