Dear All,

Hope all is going good at your end.

Query is: A user generates notification for the sake of maintenance required. As we also know the material is considered to be consumed when it is issued against 261 movement type for maintenance order.
But how can we make sure that all the material components which issued against the maintenance order were totally consumed (used) actually.

If some of the material is not used we want that the user who generated the maintenance notification should be able to enter whether all those materials which were issued are used actually? Or in how much quantity these materials were used? Can also we see those actually used materials in standing reporting? So that one can see that these quantities were issued and these were used (As reported by the maintenance request generate).