Factory Calendar Report in PM

ajaya_sahu2
Participant
0 Kudos

Dear Gurus,

Is there any report available in PM for which factory calendar is used. As factory calendar is used in Maintenance strategy , Maintenance Plan, Work centre etc. , believe some report would be available to track/list the same.

Advance thanks for the update.

Regards,

Sahu

Accepted Solutions (0)

Answers (3)

Answers (3)

anita_patil3
Explorer
0 Kudos

Hi;

Pl. elaborate the requirement in details.

Regards;

Avinash

ajaya_sahu2
Participant
0 Kudos

Dear Avinash,

Just want to know any SAP standard report for Work centre data which would provide Factory calendar details either in the output screen area or in the Input entry details.

Regards,

Ajaya

Former Member
0 Kudos

hey Sahu,

As far as I'm aware there's no such report as 'Where Used Factory Calendar'.

You'll have to work with standard list edits (i.e. IP16) and tables to check which factory calendar is used for which data object or go for a custom report.

Cheers,

Khayyam

ajaya_sahu2
Participant
0 Kudos

In IP16 report output, we can see the factory calendar. Similarly need a report to see the factory calendar assigned in work centre.

Regards,

Ajaya

Former Member
0 Kudos

For work centers I think you'll have to identify the assigned factory calendar by checking the tables, the factory calendar information is in table KAKO but you will have to find the link. Below is a list of some of the other tables which store the work center related information.

  • CRCO     -  Assignment of Work Center to Cost Center
  • CRHD     -  Work Center Header
  • CRHH     Hierarchy Header Data
  • CRHS     Hierarchy Structure
  • CRID      CIM Resource - Entities
  • CRTX     Text for the Work Center or Production Resource/Too
  • KAKO     Capacity Header Segment
  • KAKT     Capacity Description
  • KAPA     Shift Parameters for Available Capacity
  • KAPE     Capacity unit of measure allocation

Cheers,

Khayyam

peter_atkin
Active Contributor
0 Kudos

Sahu,

Maybe it would help if you explain what it is that you are trying to achieve.

PeteA

ajaya_sahu2
Participant
0 Kudos

Dear Pete,

We have few factory calendars (duplicate or unused), which we want to delete. If there is any report, it would be easier to know, which factory calendar is used on which application and redundant factory calendars can be deleted , as leads confusion. Also if any correction on data required, it would be easier to amend the correct factory calendar.

Hope get some input from your end.

Regards,