If EWM is to define a deconsolidation, one of the following cases must be present:

○  The activity areas for the products within an HU are different.

○  The activity areas for the products within an HU are the same, but the consolidation groups are different.

○  The activity areas and consolidation groups for the products within an HU are the same, but the maximum number of warehouse tasks for the HU has been exceeded.



But in my case, even though I have only one product in my HU, Warehouse task is getting created for Decon work center. So can you please suggest that what configuration I have to do so that when there is only 1 product in HU then, IB02 process step gets skipped.


Thanks in


Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 25, 2015 at 09:24 PM

    Hi All,

    Thanks for your Comments.

    Issue was resolved by making the deconsolidation step as rule based and updating work center for deconsolidation in node path:--

    SCM Extended Warehouse Management--->Extended Warehouse Management--->Goods Receipt Process--->Deconsolidation --->Specify Deconsolidation Station

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 11, 2015 at 09:23 PM

    Hi Rohit...

    This is due to POSC config. check IB02 step and destination bin. If you have given destination bin then all Hu will go via decon....

    now if you dont want that, then IB02 should be ruled based, flow same process it should resolve your issue.

    Regards

    Suraj.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 11, 2015 at 06:54 AM

    Hi Rohit,

    One way of doing this would be creating new Warehouse process type , WPT determination and assigning the PCI  to Warehouse product and don't give any storage process relevant for Deconsolidation process.

    Regards,

    Yogi

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 11, 2015 at 07:24 AM

    Hi,

    how does your process configuration look like? And rule-based is set?

    Brgds

    Juergen

    ---

    Want to learn EWM?

    Check for EWM courses @ https://training.sap.com/curriculum/scm_ewm