Material avail.date in sales order (ECC) & availability date in APO.

Hi Expert,

Looking for you help to understand the relation between material avail.date in sales order (ECC) & availability
date in APO.

Please refer attached screen print for details.

Rgds

SDB

Capture.JPG (95.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 04, 2015 at 10:26 AM

    Hello SDB,

    Can you post the screenshot of the //RRP3 ATP screen or CO09 screen. I see the discrepancy in the the MBDAT in your screenshot. But, I would like to understand if there are multiple schedule lines in the order ? Or is this the only schedule line ?


    Did you try running the /SAPAPO/SDRQCR21 program ? Did it report any inconsistency between R/3 and gATP schedule line dates ?


    Thanks & Best Regards,


    Babu Kilari