CLM Contract to SRM Central contract

Former Member
0 Kudos

Dear all

When i publish the CLM Contract to SRM, the Central contract in SRM, Would it replicate as a Saved central contract? or in 'Executed' status?

If it is editable or in saved status, if some one is changing the prize or line item detail in SRM, then it doesn't solve the purpose of having a separate CLM module right?

During the Contract replication from CLM to SRM, just would like to know what status it will go and sit in SRM?

Thanks for your valuable input in advance

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

   It will be in the saved state.. you have to do the distribution manually..

I believe the prices cannot be changed in SAP SRM. Since CLM is considered the master you can only do the changes in CLM and republish them to SRM.

Hope this answers

Former Member
0 Kudos

Thanks Venkatesh