Issue in Model Mix planning - Existing Planned Orders not sequenced

Dear Experts,

We did a R/3 system refresh recently from Production to Quality. Now I need to bring APO and R/3 in sync in quality.

We have a very limited scope of APO. We only use Model mix planning and sequencing feature of APO.

In APO, I deactivated Sales order and Planned Order integration models before R/3 refresh. Once refresh was done, through CCR I removed all Sales order and Planned Order from APO, then I activated the IMs to transfer Sales orders and Planner Orders to APO.

The activation was successful. When I checked RRP3 screen, I could see the data.

But when I ran the MMP, these planned orders were not sequenced, and in sequencing screen (SEQ1), no planned orders were displayed.

This means MMP did not consider the existing planned orders that were transferred from R/3.

The MMP only created planned orders for those new Sales orders for which planned orders were yet not created.

So my question is, is there any setting so that MMP will include the existing planned order for sequencing. I tried planning basis Order oriented but still was not successful.

Please guide. Thanks in advance!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Aug 04, 2015 at 02:58 PM

    Hi Pankit,

    To avoid this kind of issue maybe next time you could consider to do a copy for APO too in the same time with R3!

    In my opinion you have to delete all pl.orders transferred from R3 and run MMP.

    Thanks,

    Regards, MariusĀ 