What key figure should be used to load the demand planning back to ECC?

Hello,

Once the S&OP plan is approved and constrained - what right key figure that should be loaded back to execution SAP/ECC? Right signal to the planners to execute the plan.

Thanks, Renata

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Aug 02, 2015 at 03:02 PM

    Hi Renata,

    One example I have is sending the Production Receipts to ECC as PIR (Planned Independent Requirements). PIRs and dependent requirements are then used by MRP to create Planned Orders.

    Regards

    Alecsandra

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 03, 2015 at 09:51 PM

    Thanks Alecssandra.

    In our case production receipt is net out of the inventory on hand (we bring from ECC and net out the demand). If we use product receipts MRP will net out again - giving the wrong signal to the planners.

    Do you happen to have any other examples?

    Thanks