BOM change with ECN can't update to PDS

Hi,

We use the ECN to change BOM in R3 and this BOM would CIF to APO.

We would use one ECN which the vaild date is in futue to change the BOM at one time.

When today is past the valid date, we found that the PDS in APO can't update auto even we ran the CIF job every night.

Is that a standard we need to manully ran CURTO_CREATE_BOM for this?

Is there any setting in CIF or somewhere PDS can updata automatelly?

Thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Aug 07, 2015 at 05:36 AM

    Hi,

    Please check the note 1464564 that will fulfill your requirement. This note introduces BAdI method CHANGE_EFFECTIVITY_DATE of BAdI CUSLNTRTO_ADDIN which allows to move the filter horizon into past.

    Hope this helps

    Thanks

    Gomathi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 04, 2015 at 11:38 AM

    Hello,

    first of all try to examine curto_pds_chg table, does it changes at all for your scenario.

    Also you may need to apply the note 1176922 (in case you release ECN with BOM changes and want to CIF PDS to APO after release with help of regular CIF job).

    Add comment