Planning Staregy 52/50 deletion of planned order and OSS 1595312.

As per OSS 1595312 , the Planned orders that are created via planning strategy 50/52 can't be deleted manually . However it gets deleted automatically when the Demand (Planned independent requirements-PIR) are deleted.

Issue:

In order to find those demand (PIR) that triggered these planned order " I clicked on the "Pegged requirement" in Planned order . Then it shows " No pegged requirement exist".!

So how could I find the "PIR (Demand) " to delete the same?

Add comment
10|10000 characters needed characters exceeded

  • For the planned order (VP order type) created for a material A , I am able to see the Pegged one (Dependent Demand). However the DEpReq Material is the same A (Recursive) and hence it shows "No pegged requirement". (The Planned order (VP)that shows up when you click DepReq).

    Since the material has no PIR (Demand) for A and only has Planned orders and DEpReq for same Material A (Recursive), How could I get rid of the Planned orders as per OSS as it talks about deleting PIR (Demand) .

    Need help from Experts..