Hi everyone,

we are currently configuring Opportunity-Sales Quote Integration using PI. From our understanding there is supposed to be an Action in the Opportunity "Create SAP ERP Sales Quote" (or similar). We are struggling to see this Action and I was wondering what might be the case. The Problem is that we are still lacking a few settings on PI, moreover, we did not Transfer materials yet. Can someone please quickly outline the prerequisites to enable this Action on the opportunity?

We have defined the following in scoping and answered the related questions as shown below.

What else has to be the case for the Action to be available? I would expect it to be shown permenantly but disabled instead of not at all.

Cheers!
Stefan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You mentioned you did not transfer materials yet. Adding a product to an opportunity is required to see the "create SAP ERP order" action.

Regards,

Jasper

skatschewitz
Participant
0 Kudos

Hi Jasper,

thanks fot the Input. I expected that we would need materials first but could not be sure. So it is the case that the Action even only shown up once I add products to an Opportunity?! I thought that it might have been visible but disabled.

Thanks and regards,

Stefan

Former Member
0 Kudos

Yes, the action is only shown when there are products added to the opportunity.

Regards,

Jasper

Answers (2)

Answers (2)

skatschewitz
Participant
0 Kudos

Hi everyone,

just wanted to let People know that I found this document in the Service Marketplace particularly helpful: INTEGRATION: Quick Start Guide, chapter 3.

https://websmp208.sap-ag.de/~sapidb/012002523100012039452015E/C4C_QSG_1508.pdf

We have not Setup our Integration yet but I will come back and let you know once this is the case or if we nNeed additional help.

Cheers!
Stefan

chandansb
Active Contributor
0 Kudos

Hello Stefan,

Have you created the corresponding Communication Arrangement to trigger the ERP Sales Quote Request or Sales Quote?

Regards,

Chandan

skatschewitz
Participant
0 Kudos

Hello Chandan,

thanks for the quick reply. We have configured the following Communication Arrangement. Completeness Check runs successfully. Connection test of the Outbound Communication runs into Server Ping Error 303.

Should we be able to see the action once the Connection is restored?

Thanks and regards,

Stefan

chandansb
Active Contributor
0 Kudos

Stefan,

In case if you are using HCI as middleware expected ping test should give code 405 else if you are using PI it should be tested successfully.

Looks like you have some issue with the configurations, hence you are getting 303. Please re-check the configurations for this.

Regards,

Chandan

chandansb
Active Contributor
0 Kudos

Below link might be helpful for you.

Regards,

Chandan