CK11n how to set costing from-to date to be 1 day

manthana_c
Contributor
0 Kudos

Hi:

on Ck11n , I would like to set costing date from-to be valid only 1 day.

how to do pls? I have error that it always default end of month.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member198650
Active Contributor
0 Kudos

Hi Mandy,

Even you maintain the settings in the configuration, system will change the costing date to at the end of the period. It is a standard behavior of the system.

Regards,

Mukthar

manthana_c
Contributor
0 Kudos

Is there anyway to make the cost setting only for 1 day?

former_member198650
Active Contributor
0 Kudos

I think..no.

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi

Go to OKKN date control ..enter start date as "Current date" and end date also as "Current date"

So it will be for 1 day estimation and if you mark and release will effect for that day/date only

kamal