on 07-13-2015 9:39 AM
Hi Experts,
I tried to look some old posts on this issue but couldn't able to find the solution.
We have functional location task list with 5 operations, and a maintenance plan with this task list assigned.
We are calling orders manually using IP10, via releasing the call. Now, when orders are getting generated they are showing only first 3 operations.
Any suggestions?
Call object for this maintenance plan category is maintenance or service order.
Regards
DM
Greetings Deepak,
Please check whether this is a configurable task list.
If yes, note that only the valuated Operations are included and you need to provide valuation on the technical object classification level.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Strategy based Tasklist ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pete / Maria,
As of now, NO packages are selected (checked) for any operation.
But yes in change log I can see for first 3 operations some packages were maintained earlier and then deleted, and for remaining two operations no maintenance packages were maintained ever.
As said, now no packages have been maintained, and we are calling order manually in IP10; and only first 3 operations are getting copied; ideally no operation should be copied.
Please share more info about config.
Thanks for your inputs
DM
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.