WBS Basic start date don't updated according to actual finish date of previous WBS

315 Views

Dear Gurus,

i have the following scenary

Project

WBS 1

WBS 2

When i confirm all activity of first WBS element (before of schedulate date) the system update correctly the actual finish date in WBS 1 but the system during new scheduling not consider it for the next WBS2 as basic start date . The WBS2 start always in the first schedulated date 6.8.2015.

I would like this new situation after refresh scheduling activity :

Actually i have done the following scheduling setting in the project profile

I think the best scheduling method for my scenary il top down logic.

But don't understand why the system don't consider the actual finish date of the previous WBS during scheduling of following WBS element

In the previous WBS i have update all date correctly as showed below:

Thansk a lot

Daniele Pistilli

PS Team

Attachments

WBS2.png (52.3 kB)
WBS3.png (53.9 kB)
WBS4.png (52.1 kB)