Hello Team,

I have an order with 2 line items. And the sales order is in GTS block due to license determination. The actual error is like below.

Sales order#                                 Blocked / Checked

           Legal Services - Customs Document                            Blocked / Checked

10         Legal Control - Embargo                                      Released / Checked

10         Legal Control - Sanctioned Party List                        Released / Checked

10         Legal Control - License Determination                        Released / Checked)----- Material 1

20         Legal Control - Embargo                                      Released / Checked

20         Legal Control - Sanctioned Party List                        Released / Checked

20         Legal Control - License Determination                       Blocked (License Master)----- Material 2

Looking at the above error i went in GTS and i assign the required license for material 20 (Material 2) and save it after which in GTS i can see order is out of block.

Observation:

  • When i release the sales order from GTS and check in ECC under Transfer Sales document i can still see Material 20 showing as Blocked (License Master) message as it is even though it is released from GTS.

     ECC shows its Blocked under license it still allows me to create Delivery (which i guess it should not).--- Observation 1

  • As soon i create delivery i can see the message in Transfer Sales documents changed as Release/Checked for Material 20. --- Observation 2

  • Can i assign license to individual materials? As per license determination i can see all my parameters are maintained then still material 20 showed me blocked but material 1 didnt show any such message.

     Just want to understand which is the standard behaviour Observation 1 or Observation 2.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Ashutosh,

Let's take it one by one.

1) When you say you assigned license to material 20 what does it mean. Are you saying that you classified the product with valid ECCN so license can be determined. Or you manually assigned a license to the material 20.

Please confirm.

2) Are you saying that system is allowing you to create delivery even if the order is blocked. If yes, looks like you don't have copy control routine setup in ECC. Check note 741784.

3) As soon as the delivery is created, your sales order item is no longer relevant for any compliance services. So, that's okay.


Thanks

Dhilipan

Former Member
0 Kudos

Hi Dhilipan,

Point no 1 : I have assigned licnese manually to Material 20 in GTS. Determination of the license took place like it should be. (Issue solved)

Point no. 2 : Yes. System did allow me to create delivery even though order was in license block. Where as this is happening for few sales orders.

Point no. 3 : Cleared.

Regards,

Ashutosh

Former Member
0 Kudos

Any reply on this posts?????